Valaris Limited
Fleet Status Report
January 12, 2023
New Contracts and Extensions, Rig Sales and Other Updates Since Last Fleet Status Report
Floaters
Four-well contract with BP offshore Egypt for drillship VALARIS DS-12. The contract is expected to commence late in third quarter or early in fourth quarter 2023 and has an estimated duration of 320 days. The estimated total contract value, inclusive of a mobilization fee, is $136 million.
Option exercised by TotalEnergies EP Brasil offshore Brazil for drillship VALARIS DS-15. Following the exercise of this option, the rig is expected to be under contract through December 2023. There is one priced option remaining with an estimated duration of 100 days.

       Jackups
Two one-year options exercised by Harbour Energy in the UK North Sea for heavy duty harsh environment jackup VALARIS 120. The first option period is expected to commence in July 2023 in direct continuation of the existing contract.
One-well contract with Petrofac in the UK North Sea for heavy duty harsh environment jackup VALARIS 121. The contract is expected to commence early in third quarter 2023 and has an estimated duration of 70-100 days.
210-day contract with Shell in the UK North Sea for heavy duty harsh environment jackup VALARIS 121. The contract is expected to commence early in fourth quarter 2023. The expected total contract value is over $25 million. The contract has four priced options.
90-day contract with Kistos in the Dutch North Sea for heavy duty harsh environment jackup VALARIS 123. The contract commenced in November 2022. VALARIS 123 will use its selective reduction (SCR) system during the contract with Kistos to significantly reduce NOx emissions from the rig.
195-day contract with ONE-Dyas in the Dutch North Sea for heavy duty harsh environment jackup VALARIS 123. The contract is expected to commence in first quarter 2023 in direct continuation of the rig's current contract. VALARIS 123 will utilize its selective catalytic reduction (SCR) system during the contract with ONE-Dyas to significantly reduce NOx emissions from the rig.
180-day contract with Perenco in the UK North Sea for heavy duty ultra-harsh environment jackup VALARIS 247. The contract is expected to commence in first quarter 2023. The contract has one 60-day priced option.
90-day option exercised by Cantium in the U.S. Gulf of Mexico for standard duty modern jackup VALARIS 144. The option period is expected to commence in March 2023 in direct continuation of the existing contract. The operating day rate for the option period is $85,000.
One-well option exercised by Talos in the U.S. Gulf of Mexico for standard duty modern jackup VALARIS 144. The option is in direct continuation of the existing program and has an estimated duration of 30 days. The operating day rate is $86,900.
One-well contract with North Sea Natural Resources in the UK North Sea for heavy duty ultra-harsh environment jackup VALARIS Norway. The operating day rate is $105,000.

ARO Drilling
Three-year contract extension offshore Saudi Arabia for standard duty modern jackup VALARIS 147. The extension period commenced in December 2022 in direct continuation of the existing contract. In accordance with the terms of our shareholder agreement, Valaris will bareboat charter VALARIS 147 to ARO.
Three-year contract extension offshore Saudi Arabia for standard duty modern jackup VALARIS 148. The extension period is expected to commence in February 2023 in direct continuation of the existing contract. In accordance with the terms of our shareholder agreement, Valaris will bareboat charter VALARIS 148 to ARO.










New Disclosure: bolded text signifies items that have not been previously disclosed
Page 1 of 12


    
image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
Contract Backlog(1) (2)
($ millions)
202320242025+Total
Contracted Days(1) (2)
202320242025+
Drillships$554.9 $426.3 $61.1 $1,042.3 Drillships2,227 1,323 219 
Semisubmersibles228.2 110.7 — 338.9 Semisubmersibles942 487 — 
Floaters$783.1 $537.0 $61.1 $1,381.2 Floaters3,169 1,810 219 
HD - Ultra-Harsh & Harsh$195.3 $91.5 $24.6 $311.4 HD - Ultra-Harsh & Harsh1,874 718 189 
HD & SD - Modern206.0 58.7 92.7 357.4 HD & SD - Modern2,354 684 823 
SD - Legacy55.4 11.3 — 66.7 SD - Legacy749 174 — 
Jackups$456.7 $161.5 $117.3 $735.5 Jackups4,977 1,576 1,012 
Other(3)
$152.1 $87.6 $31.3 $271.0 
Other(3)
3,530 2,968 1,050 
Total$1,391.9 $786.1 $209.7 $2,387.7 Total11,676 6,354 2,281 
ARO Drilling(4)
Average Day Rates(1) (2)
202320242025+
Owned Rigs$238.5 $246.6 $336.3 $821.4 Drillships$249,000 $322,000 $279,000 
Leased Rigs269.2 280.0 101.7 650.9 Semisubmersibles242,000 227,000 — 
Total$507.7 $526.6 $438.0 $1,472.3 Floaters$247,000 $297,000 $279,000 
HD - Ultra-Harsh & Harsh$104,000 $127,000 $130,000 
HD & SD - Modern88,000 86,000 113,000 
SD - Legacy74,000 65,000 — 
Jackups$92,000 $102,000 $116,000 
(1) Contract backlog, contracted days and average day rates as of January 12, 2023.
(2) Contract backlog and average day rates exclude certain types of non-recurring revenues such as lump sum mobilization payments. Contract backlog and contracted days include backlog and days when a rig is under suspension. Average day rates are adjusted to exclude suspension backlog and days.
(3) Other represents contract backlog and contracted days related to bareboat charter agreements and management services contracts.
(4) ARO Drilling contract backlog as of January 12, 2023.
HD = Heavy Duty; SD = Standard Duty

Page 2 of 12


image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
Asset Category / RigDesignYear DeliveredCustomerLocationContract Start Date
Contract End Date(1)
Day Rate(2)
Comments
Drillships     
VALARIS DS-18GustoMSC P100002015ChevronU.S. GOMAug 22Jul 25Contract includes MPD services
VALARIS DS-17GustoMSC P100002014EquinorBrazilJun 23Dec 24
Contract includes MPD and additional services. Rig being reactivated in Spain. Total contract value of $327 million, including an upfront payment of approx. $86 million for mobilization, capital upgrades and a contribution towards reactivation costs. Two priced options each with an estimated duration of 60 days
VALARIS DS-16

GustoMSC P100002014OccidentalU.S. GOMMay 22May 24
Contract includes MPD services. 1-year priced option
VALARIS DS-15GustoMSC P100002014TotalEnergies
Brazil
Jun 21
Dec 23
Contract includes MPD services. Priced option with an estimated duration of 100 days
VALARIS DS-12
DSME 120002014
BP

Undisclosed
BP
Mauritania/Senegal
Angola
Egypt
Apr 22

Mar 23
Oct 23
Feb 23

May 23
Aug 24


Total contract value of $26.2 million
Total contract value of $136 million
VALARIS DS-10
Samsung GF120002017SNEPCoNigeriaApr 22Apr 23Priced option with an estimated duration of 330 days
VALARIS DS-9Samsung GF120002015ExxonMobilAngolaJul 22Jul 24
Contract includes MPD services. Four 6-month priced options
VALARIS DS-4Samsung 96K2010PetrobrasBrazilJul 22Dec 23
Contract includes MPD and additional services. 6-month priced option
Stacked
VALARIS DS-11DSME 120002013Spain
VALARIS DS-8
Samsung GF120002015Spain
VALARIS DS-7
Samsung 96K2013Spain
Purchase Options(3)
VALARIS DS-14

DSME 12000South KoreaOption to take delivery by year-end 2023. Purchase price of approx. $218 million assuming a Dec 31, 2023 delivery
VALARIS DS-13


DSME 12000South KoreaOption to take delivery by year-end 2023. Purchase price of approx. $119 million assuming a Dec 31, 2023 delivery
Changes: bolded rig names and underlined text signify changes in rig status from previous report
Page 3 of 12


image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
Asset Category / RigDesignYear DeliveredCustomerLocationContract Start Date
Contract End Date(1)
Day Rate(2)
Comments
Semisubmersibles
VALARIS DPS-5


ENSCO 8500 Series,
DP + Moored
2012Murphy
Murphy
Eni
U.S. GOM
Mexico
Mexico
Sep 22
Oct 22
Jan 23
Oct 22
Dec 22
Aug 23


$313,500


Plus mobilization fee of approx. $1.2 million
VALARIS DPS-1


F&G ExD Millennium, DP2012Woodside
Woodside

Australia
Australia

Apr 22
Mar 23
Mar 23
Sep 24
VALARIS MS-1


F&G ExD Millennium, Moored2011Santos




Undisclosed
Australia




Australia
Jul 22




Oct 23
Oct 23




Aug 24
Contract suspended. During the contract suspension period, the duration of which is currently unknown, we do not expect a material impact on revenues and earnings. Three priced options each with an estimated duration of 50 days
Stacked
VALARIS DPS-6
ENSCO 8500 Series, DP2012U.S. GOM
VALARIS DPS-3
ENSCO 8500 Series,
DP + Moored
2010U.S. GOM
Changes: bolded rig names and underlined text signify changes in rig status from previous report


Page 4 of 12


image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
Asset Category / RigDesignYear DeliveredCustomerLocationContract Start Date
Contract End Date(1)
Day Rate(2)
Comments
Jackups      
Heavy Duty Ultra-Harsh Environment(4)
VALARIS NorwayKFELS N Class2011
BP
Centrica Storage
North Sea Natural Resources
UK
UK
UK
May 22
Jan 23
Aug 23

Nov 22
Apr 23
Sep 23



$105,000
VALARIS StavangerKFELS N Class2011Equinor
Norway
UK
Oct 19Nov 22
VALARIS VikingKFELS N Class2010RepsolNorwayJun 22Jan 23
VALARIS 250LT Super Gorilla XL2003Saudi AramcoSaudi ArabiaJun 18Dec 24
Leased to ARO Drilling(5)
VALARIS 249LT Super Gorilla2002OMVNew ZealandFeb 22Apr 23
VALARIS 248LT Super Gorilla2000NeptuneUKAug 20Dec 23
VALARIS 247LT Super Gorilla1998
DNO
Perenco
UK
UK
May 21
Mar 23
Jan 23
Sep 23

One priced option with an estimated duration of 60 days
Changes: bolded rig names and underlined text signify changes in rig status from previous report
Page 5 of 12


image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
Asset Category / RigDesignYear DeliveredCustomerLocationContract Start Date
Contract End Date(1)
Day Rate(2)
Comments
Jackups     
Heavy Duty Harsh Environment(4)
 
VALARIS 123KFELS Super A2019Kistos
ONE-Dyas
Netherlands
Netherlands
Nov 22
Feb 23
Feb 23
Aug 23
VALARIS 122


KFELS Super A2014Shell
Shell
Shell
UK
UK
UK
Jan 20
Nov 22
Apr 23
Nov 22
Apr 23
Aug 24


Total contract value of over $60 million
VALARIS 121KFELS Super A2013
Harbour Energy
Petrofac
Shell
UK
UK
UK
Jul 21
Jul 23
Oct 23
Jan 23
Sep 23
Apr 24


Total contract value of over $25 million. Four priced options
VALARIS 120KFELS Super A2013Harbour EnergyUK
Jul 17
Jul 23
Jul 23
Jul 25
Stacked
VALARIS 102KFELS MOD V-A2002U.S. GOM
Changes: bolded rig names and underlined text signify changes in rig status from previous report

Page 6 of 12


image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
Asset Category / RigDesignYear DeliveredCustomerLocationContract Start Date
Contract End Date(1)
Day Rate(2)
Comments
Jackups
Heavy Duty - Modern(4)
VALARIS 118LT 240-C2011BP
BP
Trinidad
Trinidad
Oct 22
Jul 23
Jun 23
Jan 24

Total contract value of approx. $24 million
VALARIS 117LT 240-C2009EniMexicoDec 21Dec 23
VALARIS 116LT 240-C2008Saudi AramcoSaudi ArabiaDec 18Dec 24
Leased to ARO Drilling(5)
VALARIS 115BM Pacific Class 4002013Mubadala Petroleum

Shell
Thailand
Singapore
Brunei
Feb 22

Apr 23
Nov 22

Apr 27

SPS and contract preparations
Total contract value of approx. $159 million
VALARIS 110KFELS MOD V-B2015North Oil CompanyQatarOct 21Oct 24Two 1-year priced options
VALARIS 108KFELS MOD V-B2007Saudi Aramco
Saudi Arabia
Nov 18Mar 23
VALARIS 107KFELS MOD V-B2006Undisclosed
Eni

GB Energy
Undisclosed
Australia
Australia

Australia
Australia
Aug 22
Nov 22

Feb 23
Apr 23
Nov 22
Feb 23

Apr 23
Jul 23
$112,000
$115,000

$118,000
$120,000

One priced option with an estimated duration of 30 days
VALARIS 106KFELS MOD V-B2005BPIndonesia
Jan 18
Jan 24
Eight priced options each with an estimated duration of 90 days
Stacked
VALARIS 111KFELS MOD V-B2003Croatia
VALARIS 109KFELS MOD V-Super B2008Namibia
VALARIS 104KFELS MOD V-B2002UAE
Changes: bolded rig names and underlined text signify changes in rig status from previous report
Page 7 of 12


image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
Asset Category / RigDesignYear DeliveredCustomerLocationContract Start Date
Contract End Date(1)
Day Rate(2)
Comments
Jackups
Standard Duty - Modern
VALARIS 148LT Super 116-E2013Saudi AramcoSaudi ArabiaNov 19Feb 26
Leased to ARO Drilling(5)
VALARIS 147LT Super 116-E 2013Saudi AramcoSaudi ArabiaSep 19Dec 25
Leased to ARO Drilling(5)
VALARIS 146LT Super 116-E2011Saudi AramcoSaudi ArabiaSep 18Dec 24
Leased to ARO Drilling(5)
VALARIS 144LT Super 116-E2010
Undisclosed
Cantium
Talos
U.S. GOM
U.S. GOM
U.S. GOM
Aug 22
Dec 22
Jul 23
Nov 22
Jun 23
Sep 23

$80,000
$86,900
Total contract value of approx. $5 million
90-day priced option
VALARIS 143LT Super 116-E 2010Saudi AramcoSaudi ArabiaOct 18Dec 24
Leased to ARO Drilling(5)
VALARIS 141LT Super 116-E2016Saudi AramcoSaudi ArabiaAug 22Aug 25
Leased to ARO Drilling(5)
VALARIS 140LT Super 116-E2016Saudi Aramco
Saudi ArabiaMar 22Mar 25
Leased to ARO Drilling(5)
VALARIS 76LT Super 116-C2000Saudi Aramco
Saudi Arabia
Jan 15
Oct 23
Stacked
VALARIS 75LT Super 116-C 1999U.S. GOM
Changes: bolded rig names and underlined text signify changes in rig status from previous report
Page 8 of 12


image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
Asset Category / RigDesignYear DeliveredCustomerLocationContract Start Date
Contract End Date(1)
Day Rate(2)
Comments
Jackups
Standard Duty - Legacy 
VALARIS 92LT 116-C1982Harbour EnergyUKFeb 17Dec 23
VALARIS 72Hitachi K1025N1981Eni
UK
Jan 20

Jun 24
VALARIS 54F&G L-780 Mod II-C1982Saudi AramcoSaudi ArabiaSep 14Mar 23
Held for Sale
VALARIS 145LT Super 116-E2010U.S. GOM
Changes: bolded rig names and underlined text signify changes in rig status from previous report


Page 9 of 12


image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
Asset Category / RigDesignCustomerLocationContract Start Date
Contract End Date(1)
Day Rate(2)
Comments
Other
Drilling Management 
Thunder HorseDeepwater SemisubmersibleBPU.S. GOMJan 17Jan 24
Mad DogDeepwater Spar Drilling RigBPU.S. GOMJan 17Jan 24
ARO Drilling
Jackup Rigs Owned by ARO Drilling 
ARO 2001LT 116-CSaudi AramcoSaudi ArabiaOct 17Jan 26
ARO 2003BM 200-HSaudi AramcoSaudi ArabiaFeb 18Feb 26
ARO 3001LT Tarzan 225-CSaudi AramcoSaudi ArabiaOct 17Jan 26
ARO 3002LT Tarzan 225-CSaudi AramcoSaudi ArabiaOct 17Jan 26
ARO 3003LT Tarzan 225-CSaudi AramcoSaudi ArabiaOct 18Dec 26
ARO 3004LT Tarzan 225-CSaudi AramcoSaudi ArabiaOct 18Dec 26
ARO 4001KFELS Super BSaudi AramcoSaudi ArabiaOct 17Jan 26
ARO 2005LT 116-CSaudi ArabiaUnder construction. Delivery expected in 2023
ARO 2006LT 116-CSaudi ArabiaUnder construction. Delivery expected in 2023
Changes: bolded rig names and underlined text signify changes in rig status from previous report
(1) Contract duration does not include any unexercised optional extensions. Contract end dates can vary based on how long it takes to complete the wells subject to the contract.
(2) Day rates are provided unless such disclosures are restricted by confidentiality provisions.
(3) Valaris has the right, but not the obligation, to take delivery of either or both rigs on or before December 31, 2023. Not included in Valaris' fleet count.
(4) Heavy duty jackups are well-suited for operations in tropical revolving storm areas.
(5) Rigs leased to ARO Drilling via bareboat charter agreements to fulfill contracts between ARO Drilling and Saudi Aramco.
Page 10 of 12


fsrglobalfleetmap_1122023x.jpg
Page 11 of 12


image6a.jpg
Valaris Limited
Fleet Status Report
January 12, 2023
 
Additional Information Regarding this Fleet Status Report
 
Day Rate and Terms. The day rates reflected in this Fleet Status Report are stated in U.S. dollars and are the operating day rates charged to customers, which may include estimated contractual adjustments for changes in operating costs and/or reimbursable cost adjustments for ongoing expenses such as crew, catering, insurance and taxes. The day rates, however, do not include certain types of non-recurring revenues such as lump sum mobilization payments, revenues earned during mobilizations, revenues associated with contract preparation and other non-recurring reimbursable items such as mobilizations and capital enhancements, and the impact of the fair market value adjustments to previously acquired drilling contracts. Routine and non-routine downtime may reduce the actual revenues recognized during the contract term. Additionally, we sometimes negotiate special rates and/or day rate adjustments with customers that may reduce revenues recognized.

Total Contract Value. Total contract value is the estimated total compensation expected to be received for a contract, including the operating day rate over the estimated firm term of the contract and any non-recurring lump sum payments for items such as mobilization, reactivation and capital upgrades.
 
Forward-Looking Statements. Statements contained in this Fleet Status Report that are not historical facts are forward-looking statements within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. Forward-looking statements include words or phrases such as "anticipate," "believe," "estimate," "expect," "intend," "likely," "plan," "project," "could," "may," "might," "should," "will" and similar words and specifically include statements regarding future rig day rates, including adjustments with customers; future levels of offshore drilling activity; expected utilization, day rates, revenues, operating expenses, rig commitments and availability, cash flow, contract status, terms and duration, contract backlog, capital expenditures, insurance, financing and funding; the effect, impact, potential duration and other implications of COVID-19; the offshore drilling market, including supply and demand, customer drilling programs, stacking and reactivation of rigs, effects of new and reactivated rigs on the market and effects of volatility in commodity prices; expected work commitments, awards and contracts; letters of intent; scheduled delivery dates for rigs; performance of our joint venture with Saudi Aramco; the timing of delivery, mobilization, contract commencement, availability, relocation or other movement of rigs; expected divestitures of assets; general market, business and industry conditions, trends and outlook; general political conditions, including political tensions, conflicts and war (such as the ongoing conflict in Ukraine); future operations; increasing regulatory complexity; and expense management. The forward-looking statements contained in this press release are subject to numerous risks, uncertainties and assumptions that may cause actual results to vary materially from those indicated, which may, among other things, impact our ability to staff rigs and rotate crews; cancellation, suspension, renegotiation or termination of drilling contracts and programs, including drilling contracts which grant the customer termination rights if final investment decision (FID) is not received with respect to projects for which the drilling rig is contracted; potential additional asset impairments; failure to satisfy our debt obligations; our ability to obtain financing, service our debt, fund capital expenditures and pursue other business opportunities; adequacy of sources of liquidity for us and our customers; the effects of our emergence from bankruptcy on the Company's business, relationships, comparability of our financial results and ability to access financing sources; actions by regulatory authorities, or other third parties; actions by our security holders; commodity price fluctuations and volatility, customer demand, new rig supply, downtime and other risks associated with offshore rig operations; severe weather or hurricanes; changes in worldwide rig supply and demand, competition and technology; consumer preferences for alternative fuels; increased scrutiny of our Environmental, Social and Governance ("ESG") practices and reporting responsibilities; changes in customer strategy; governmental action, civil unrest and political and economic uncertainties; the COVID-19 outbreak and the related public health measures implemented by governments worldwide, terrorism, piracy and military action; risks inherent to shipyard rig reactivation, upgrade, repair, maintenance or enhancement; our ability to enter into, and the terms of, future drilling contracts; suitability of rigs for future contracts; the cancellation of letters of intent or letters of award or any failure to execute definitive contracts following announcements of letters of intent, letters of award or other expected work commitments; the outcome of litigation, legal proceedings, investigations or other claims or contract disputes; governmental regulatory, legislative and permitting requirements affecting drilling operations; our ability to attract and retain skilled personnel on commercially reasonable terms; environmental or other liabilities, risks or losses; debt restrictions that may limit our liquidity and flexibility; and cybersecurity risks and threats. In addition to the numerous factors described above, you should also carefully read and consider "Item 1A. Risk Factors" in Part I and "Item 7. Management’s Discussion and Analysis of Financial Condition and Results of Operations" in Part II of our most recent annual report on Form 10-K, which is available on the SEC’s website at www.sec.gov or on the Investor Relations section of our website at www.valaris.com. Each forward-looking statement speaks only as of the date of the particular statement, and we undertake no obligation to update or revise any forward-looking statements, except as required by law.